Return to Portfolio

Iron Mountain AZP2 Data Center

Market Sector

Advanced Technology

Location

Phoenix, AZ

Owner

Iron Mountain

Architect

Corgan

Contractor

Coreslab Structures

Holder Construction

Construction Type

Pre-Cast Concrete

Steel Frame

Phoenix is one of the fastest growing data center markets in the United States. To keep up with demand, Iron Mountain’s Phoenix Data Center Campus expanded with a new 547,000 SF 48-megawatt data center. The pre-cast concrete data center includes a rooftop mechanical yard for cooling towers and chillers, secure storage, 12 data halls, loading docks, and a 2-story 38,000 SF structural steel framed office area. One of the largest data centers in Arizona, Iron Mountain AZP-2 supports ISO 27001, FISMA High, PCI-DSS Level 1, HIPAA, SOC 2 Type II and SOC 3, and is located on a 39-acre site shared with their existing 38-megawatt data center, AZP-1.

Take a tour of AZP-2

Want to find out more about this project?

Don’t hesitate to ask.

Contact Us