Return to Portfolio

Phoenix Sky Harbor International Airport (PSHIA) T4 Central Plant Modernization

Market Sector

Aviation

Location

Phoenix, AZ

Owner

City of Phoenix

Architect

SmithGroup

Contractor

Holder Construction

Construction Type

Steel Frame

Concrete over Steel Deck

Masonry Walls

The modernization project of the nearly 30-year-old central utility plant includes replacing the plants chillers, heat exchangers, cooling towers, condensing water pumps, chilled water piping, and central plant piping. A multi-phased design ensured this essential facility remained operational throughout construction.

A 60’ tall steel framed tower provided support for temporary vertical pipe runs that extend through existing concrete exterior walls to serve cooling towers at the fourth level. The existing structure was evaluated for new, heavier equipment, water-filled pipes up to 36″-diameter, and new penetrations and shafts. Detailed analyses nearly eliminated the need to strengthen the existing structure. New Level Two framing infill provides additional floor space at the Apron level for future equipment.

Structural coordination accounted for varying pipe locations throughout each project phase. Steel pipe supports were strategically located to engage the existing structure and provide sufficient capacity for added loads while avoiding clashes with phase-specific piping layouts.